Phase 1 - EMWD COMPLETED
Install two 18" water lines under Fir Ave. east of Nason St.
Phase 2 - SCE
COMPLETED Replace overhead distribution lines along SR-60 between Morrison and Moreno Beach Dr. with underground distribution lines ... more information
Phase 3 - SR/60 Nason St. Interchange Improvements Start: 10/10 - Complete: 9/11 Reconstruct and realign Nason Street on/off ramps to State Route 60.
January 15, 2010 Phase 2 Southern California Edison work was completed on January 15, 2010 ... read more
September 25, 2009 SCE will begin underground cabling next week ... read more
October 1, 2009 SR-60/Nason St. Project Website launches ... read more
Construction ... Your Dollars at Work
[ Click image to enlarge ]
Moreno Valley is proud to present the SR-60/Nason Street Interchange Improvement Project. This project will reconstruct and realign Nason Street on/off ramps to State Route 60. Utility relocation is being coordinated with Eastern Municipal Water District (EMWD) and Southern California Edison (SCE) utility companies in advance of the proposed Nason Street Interchange Improvement ... more information